Titagarh Rail Systems Limited is looking for a Project/Production Planning & Control Specialist with experience in Rolling Stock or Automotive industry.
Years of Experience required: 4-10yrs
KRA:
• Understand work scope, quantity and familiar with logical sequences in terms of engineering, manufacturing and construction disciplines.
• Understand WBS structure and work with management & project/method team in the development of work break down structure for progress measurement, scheduling, cost estimating and project control.
• Prepare and manage overall master schedule integrating work breakdown structure using scheduling software Primavera/ MS Project.
• Understand contractual matter, earn value method, familiar with scope management and change control.
• Coordinate schedule from multiple stakeholders and incorporate the information gathered into the overall project master schedule.
• Prepare cost estimation and schedule bar chart plan considering all in puts (manpower, equipment and materials) availability, production and process sequences.
• Develop work method of statement or procedure as required.
• Understand and able to utilize planning tools such as MS excel, MS Project, Primavera, SAP and ERP.
• Develop and update resource (manpower and equipment) histogram weekly or monthly as required.
• Evaluate allocation of resources and provide recommendations to maintain required progress.
• Develop and implement plan versus actual progress charts (histograms/S curves). Reports and analyses deviations from plan.
• Track, monitor and forecast progress of all activities and deliverable such as products, engineering documents, fabrication status and construction of all discipline.
• Analyse gaps between the planned and actual progress and highlight the areas of concern which required action of the associate task member.
• Perform probabilistic analysis of completion dates and potential alternatives. Present risk-based analysis of most likely completion and expected deviation range.
• Prepare and update three weeks and three months look-ahead schedule that reflect the priority activities
• Liaises with all team leaders and/or members to communicate required completion dates and interface between functional team/operational team and project team.
• Lead CFT meeting (i.e., schedule review meeting, progress meeting, coordination meeting, constructability review meeting and so on).
• Supervise a team of planning specialists, analysts, and other staff members.
Qualification: Full time B.Tech / Diploma (Mech / Elec. Engg)